Transmission Line 705 Project
About the Project
The Transmission Line 705 (TL705) project is the proposed construction of a new 138 kilovolt (kV) underground transmission cable that spans approximately 5.5 miles between two area substations in the Town of Clarkstown, Rockland County, New York. Construction is due to begin on or about September 24, 2024.
The proposed route goes from west to east from the Burns Substation access road, beneath N. Pascack Rd, onto Smith Rd, then south on N. Middletown Rd, east onto Rt. 59, north on College Ave, east on West Nyack Rd, then onto Western Highway North, turning east and running beneath the CSX railroad tracks and onto the West Nyack Substation property.
This project will provide additional electric power to the southern Rockland County area, making the system more robust and safe, and improving service reliability.
Permitting and Approvals
To construct the Project, O&R will need all the necessary permits/approvals:
Federal Permits:
- U.S. Army Corps of Engineers
- Notification to New York State Thruway Authority
State Permits/Approvals:
- New York State Public Service Commission under Article VII of the Public Service Law, the Certificate of Environmental Compatibility and Public Need.
- Environmental Management & Construction Plan (EM&CP)
- New York State Department of Transportation – Utility Work Permit
Municipality Permits:
- Local approval from the Rail Road Crossing
- Consultation with Town of Clarkstown and the municipalities along the route
Where to Find Our Filings
Documents related to this project have been filed and can be found at the following libraries:
- Nanuet Public Library – 149 Church St, Nanuet, NY 10954 – (845) 623-4281
- West Nyack Free Library – 65 Strawtown Rd, West Nyack, NY 10994 – (845) 358-6081
- New City Library – 220 N. Main St, New City, NY 10956 – (845) 634-4997
|
Document |
Date |
| Public Involvement Plan (PDF) | December 2019 |
| Engineering Management and Construction Plan | March 2024 |
| Notice of the Start of Construction | September 2024 |
Project Status
Week beginning - Monday, October 6, 2025:
- Install transmission manholes along N Middletown Rd.
- Install distribution & transmission duct banks along N Pascack Rd. & NMiddletown Rd. interconnecting transmission manholes
- Excavate and install fiber handholds
- Restoration along N Middletown Rd. and W Nyack Rd.
Week beginning - Monday, October 13, 2025:
- Install distribution pull boxes along N Pascack Rd.
- Install distribution & transmission duct banks along N Pascack Rd. to Smith Rd. interconnecting manholes
- Restoration along N Pascack Rd. to Smith Rd.
Week beginning - Monday, October 20, 2025:
- Install distribution & transmission duct banks along W Nyack Rd. and from N Pascack Rd. towards Rt 59 interconnecting manholes
- Begin Rt 304 crossing work
Week beginning - Monday, October 27, 2025:
- Complete installation along N Pascack Rd., and Rt 304 crossing along W Nyack Rd.
- Complete restoration of disturbed areas and make construction areas safe for Halloween