Transmission Line 705 Project
About the Project
The Transmission Line 705 (TL705) project is the proposed construction of a new 138 kilovolt (kV) underground transmission cable that spans approximately 5.5 miles between two area substations in the Town of Clarkstown, Rockland County, New York. Construction is due to begin on or about September 24, 2024.
The proposed route goes from west to east from the Burns Substation access road, beneath N. Pascack Rd, onto Smith Rd, then south on N. Middletown Rd, east onto Rt. 59, north on College Ave, east on West Nyack Rd, then onto Western Highway North, turning east and running beneath the CSX railroad tracks and onto the West Nyack Substation property.
This project will provide additional electric power to the southern Rockland County area, making the system more robust and safe, and improving service reliability.
Permitting and Approvals
To construct the Project, O&R will need all the necessary permits/approvals:
Federal Permits:
- U.S. Army Corps of Engineers
- Notification to New York State Thruway Authority
State Permits/Approvals:
- New York State Public Service Commission under Article VII of the Public Service Law, the Certificate of Environmental Compatibility and Public Need.
- Environmental Management & Construction Plan (EM&CP)
- New York State Department of Transportation – Utility Work Permit
Municipality Permits:
- Local approval from the Rail Road Crossing
- Consultation with Town of Clarkstown and the municipalities along the route
Where to Find Our Filings
Documents related to this project have been filed and can be found at the following libraries:
- Nanuet Public Library – 149 Church St, Nanuet, NY 10954 – (845) 623-4281
- West Nyack Free Library – 65 Strawtown Rd, West Nyack, NY 10994 – (845) 358-6081
- New City Library – 220 N. Main St, New City, NY 10956 – (845) 634-4997
|
Document |
Date |
| Public Involvement Plan (PDF) | December 2019 |
| Engineering Management and Construction Plan | March 2024 |
| Notice of the Start of Construction | September 2024 |
Project Status
Week beginning - Saturday, November 15, 2025 (County Deadline):
- Continue installing duct banks along North Middletown Road in east lane of road from Station 117+00 to 134+00.
- Set Transmission Manhole #9, Backfill and restore asphalt.
- Tie-pipes into Transmission Manhole #9.
Week beginning - Monday, November 17, 2025:
- Continue installing duct banks along West Nyack Road.
- Begin duct banks on Smith Road to crossroad to north side at Nauraushaun Brook
- Saw cutting West Nyack Road
- Test pits West Nyack Road.
- Hammer Roadway concrete in West Nyack Road.
-
Install Fiber Hand Hold #21.
Week beginning - Saturday, November 22, 2025 (County Deadline):
- Continue installing duct banks West Nyack Road.
- Saw cutting West Nyack Road
- Test pits West Nyack Road.
- Hammer Roadway concrete in West Nyack Road
Week beginning - Monday, November 24, 2025:
- Continue installing duct banks along West Nyack Road.
- Saw cutting West Nyack Road.
- Test pits West Nyack Road.