Skip to Main Content
ajax loader animation
ajax loader animation
large spools of underground cable

Transmission Line 705 Project

In order to provide more reliable electric service to our customers in southern Rockland County, O&R is proposing to install a new transmission line in the Town of Clarkstown.

About the Project

The Transmission Line 705 (TL705) project is the proposed construction of a new 138 kilovolt (kV) underground transmission cable that spans approximately 5.5 miles between two area substations in the Town of Clarkstown, Rockland County, New York. Construction is due to begin on or about September 24, 2024.

The proposed route goes from west to east from the Burns Substation access road, beneath N. Pascack Rd, onto Smith Rd, then south on N. Middletown Rd, east onto Rt. 59, north on College Ave, east on West Nyack Rd, then onto Western Highway North, turning east and running beneath the CSX railroad tracks and onto the West Nyack Substation property.

This project will provide additional electric power to the southern Rockland County area, making the system more robust and safe, and improving service reliability.

Back to top

Permitting and Approvals

To construct the Project, O&R will need all the necessary permits/approvals:

Federal Permits:

  • U.S. Army Corps of Engineers
  • Notification to New York State Thruway Authority

State Permits/Approvals:

  • New York State Public Service Commission under Article VII of the Public Service Law, the Certificate of Environmental Compatibility and Public Need.
  • Environmental Management & Construction Plan (EM&CP)
  • New York State Department of Transportation – Utility Work Permit

Municipality Permits:

  • Local approval from the Rail Road Crossing
  • Consultation with Town of Clarkstown and the municipalities along the route
Back to top

Where to Find Our Filings

Documents related to this project have been filed and can be found at the following libraries:

  • Nanuet Public Library – 149 Church St, Nanuet, NY 10954 – (845) 623-4281
  • West Nyack Free Library – 65 Strawtown Rd, West Nyack, NY 10994 – (845) 358-6081
  • New City Library – 220 N. Main St, New City, NY 10956 – (845) 634-4997

Document

Date
 Public Involvement Plan (PDF)  December 2019
Engineering Management and Construction Plan  March 2024
Notice of the Start of Construction  September 2024
Back to top

June 1st, 2026, through July 2nd, 2026:

June 1st through June 6th, 2026:

  • Continue transmission & distribution ductbank installation along W. Nyack Rd, heading past Demarest Ave. Interconnection on more manhole sections.
  • Continue transmission ductbank and takeoff structure foundation work at Burns substation. 
  • Finish distribution storm hardening ductbank installation along W. Nyack Rd., & Demarest Ave.
  • Taihan Electric/New River Electric to continue Transmission Cable installation along W.Nyack Rd. and continue splicing. 
  • More interconnections into transmission manholes and Saturday work tru-taping, and restoration, and cable installation.

June 8th through June 13th, 2026:

  • Mobilize subcontractor for CSX bore, begin layout and deliver material onsite. 
  • Continue transmission ductbank installation along W. Nyack Rd and Western Highway.
  • More interconnections into transmission manholes and Saturday work tru-taping, and restoration, and cable installation.
  • Taihan Electric/New River Electric to continue Transmission Cable installation along W. Nyack Rd. and continue splicing where available. 

June 15th through June 20th, 2026:

  • Excavate pits and setup equipment involved with CSX bore.
  • Pre-con meeting for the Rt. 304 crossing along W. Nyack Rd. 
  • Continue transmission ductbank installation along W. Nyack Rd and Western Highway.
  • Taihan Electric/New River Electric to continue Transmission Cable installation along W. Nyack Rd. and continue splicing where available. 
  • Smith Rd. culvert crossing field meeting for final interconnection along Smith Rd.
  • More interconnections into transmission manholes and Saturday work tru-taping, and restoration, and cable installation.  

June 22nd through June 27th, 2026:

  • Continue installation of casing underneath CSX railroad.
  • Complete ductbank installation along Rt. 304 crossing W. Nyack Rd. 
  • Taihan Electric/New River Electric to continue Transmission Cable installation along W. Nyack Rd. and continue splicing where available. 
  • More interconnections into transmission manholes and Saturday work tru-taping, and restoration, and cable installation.

June 29th through July 2nd, 2026:

  • Complete Rt. 304 restoration, site cleanup if necessary.
  • Continue installation of casing underneath CSX railroad.
  • Complete ductbank installation along Rt. 304 crossing W. Nyack Rd. 
  • Taihan Electric/New River to continue cable installation and splicing.
  • Full site restoration and cleanup by Thursday midday in anticipation of Independence Day weekend.  
  • No work being done Friday or Saturday
     

Back to top