Installations Up To 2MW

Please follow the guidelines below for installation of systems that generate up to 2MW.

Standards and applications can be found in the New York State Standardized Interconnection Requirements. In most cases, the certified installer handles the technical paperwork. Please verify this with the installer.

Commercial Customers:

Please review the following applicable tariffs and contact an account engineer in the New Construction office at 845-577-3424, before beginning the application process below:

Prior to installation:
  1. Applicants should send:
    • Appendix A (Standardized Contract)
    • Appendix B or Appendix C (Standardized Application)
    • one-line electrical schematic and inverter information ( For installations more than 15kW, a $350 application fee will be assessed.)
  2. O&R will review the application and design.
  3. O&R will either give approval to install the system or explain why approval was not granted.
Upon completion of installation:
  1. Applicants should send in proof of electrical inspection.
  2. O&R will witness a verification test.
  3. If verification test passes, O&R will return the executed agreement to applicant. (The system should not be put in service, except for initial testing, until after the verification test.)
  4. If the installation is eligible for net metering, O&R will change the revenue meter.
Installations Greater Than 2MW

Please follow the applicable guidelines below for installation of systems that generate more than 2MW: